Fourth Street Road Replacement and Closure
All-UA
Fourth Street Road Replacement and Closure
To: Campus Community
Christopher M. Kopach, Assistant Vice President, Facilities Management
Subject: Fourth Street Road Replacement and Closure
Date: May 16, 2013
UNIVERSITY OF ARIZONA STREET REPAIR NOTICE
4th Street Road Replacement
5/16/13
Facilities Management will start the curb and street replacement on the following dates.
Phase 1: May 20-24, 2013 - Curb Work
· Remove and replace 488’ of curbs
· Work to be performed 8pm-5am
· 4th Street will remain open
Phase 2: June 4-7, 2013 - Street Replacement
· Remove and Repave
· Highland North – From Southern 4th Street to Northern 4th Street
· 4th Street – from Highland to West side of East entrance Science Library Parking Lot (6088)
· This portion of street will be closed during this time
Phase 3: June 10-14, 2013 - Street Replacement
· Remove and Repave
· 4th Street – From West side of East entrance of Science Library Parking Lot (6088) to East side of West entrance of Bear Down Field.
· This portion of street will be closed during this time
Phase 4: June 17-21, 2013 - Street Replacement
· Remove and Repave
· 4th Street East side of West entrance of Bear Down Field to Cherry from North crosswalk at 4th Street, South to NEZ project concrete
· This portion of street will be closed during this time.
If you have questions, please contact Luis H. Rocha, Associate Director, Facilities Management at 241-7254 or rochal@email.arizona.edu.